Kemajuan Pekerjaan Infrastruktur Permukiman

Filter

Kolom

Total Realisasi Progres
KOTA PALU
Construction of Water Distribution Pipe and House Connection in Kota Palu
SR
4000.00 Unit
100%
KOTA PALU
Construction of Water Distribution Pipe and House Connection in Kota Palu
Pipa JDP
127010.02 M
100%
KOTA PALU
Construction of Water Distribution Pipe and House Connection in Kota Palu
JDU
3413.04 M
100%
KABUPATEN SIGI
Construction of Bora SPAM IKK Piping Network for Huntap Pombewe, Kab. Sigi
INTEK
1.00 Unit
100%
KABUPATEN SIGI
Construction of Bora SPAM IKK Piping Network for Huntap Pombewe, Kab. Sigi
Hidran Umum
2.00 Unit
100%
KABUPATEN SIGI
Construction of Bora SPAM IKK Piping Network for Huntap Pombewe, Kab. Sigi
Pipa Transmisi
52.00 M
100%
KABUPATEN SIGI
Construction of Bora SPAM IKK Piping Network for Huntap Pombewe, Kab. Sigi
Reservoir
3.00 Unit
100%
KABUPATEN SIGI
Construction of Bora SPAM IKK Piping Network for Huntap Pombewe, Kab. Sigi
IPA/RESERVOIR
1.00 Unit
100%
KOTA PALU
Optimalization of IPLT in Kota Palu and Kabupaten Sigi
IPLT
1.00 M
100%
KOTA PALU
Construction of Water Treatment Plant 2x30 L/s for Huntap Tondo 1, Tondo 2 & Talise, Kota Palu
Reservoir
2.00 Unit
100%